🏠 Home
AQA A-Level Business · 7132

Investment
Appraisal

Payback period, ARR, net present value — how businesses evaluate capital investments

⏳ Payback period 📊 ARR 💰 Net Present Value ⏱ 26 min 📝 3 practice questions
Learning Objectives

By the end of this lesson you will be able to…

Method 1

Payback Period

Definition

The time taken for cumulative cash inflows to equal the initial investment.

If investment = £100,000 and annual inflow = £25,000 → Payback = 4 years

YearCash Flow (£)Cumulative (£)
0 (Investment)−100,000−100,000
Year 130,000−70,000
Year 235,000−35,000
Year 340,000+5,000 ✓
Payback period2 years 10.5 months
Payback within Year 3: £35,000 needed; £40,000 arrives in Year 3 → 35,000/40,000 × 12 = 10.5 months into Year 3. Total payback = 2 years 10.5 months.

Pros: Simple; good for cash-constrained firms; focuses on liquidity risk. Cons: Ignores cash flows after payback; ignores time value of money.
Method 2

Average Rate of Return (ARR)

Formula

ARR (%) = (Average Annual Profit ÷ Initial Investment) × 100

Average annual profit = Total net cash flows ÷ Number of years

Method 3: Most Sophisticated

Net Present Value (NPV)

Time Value of Money

£1 today is worth more than £1 in the future — due to inflation, opportunity cost and risk. NPV discounts future cash flows back to their present value using discount factors.

Decision Rule

NPV = Sum of all discounted cash inflows − Initial investment

Accept if NPV > 0 (project generates more than the cost of capital). Reject if NPV < 0.

YearCash Flow (£)Discount Factor @10%Present Value (£)
150,0000.90945,450
260,0000.82649,560
370,0000.75152,570
Total PV of inflows147,580
Less: Initial Investment−120,000
NPV+27,580 → ACCEPT
Method Comparison

Strengths & Weaknesses

Payback — Best for:

  • Cash-constrained SMEs needing quick returns
  • Fast-changing markets where long forecasts are unreliable
  • Simple comparison between projects
  • Weakness: Ignores total profitability

ARR — Best for:

  • Comparing % returns across projects of different sizes
  • When all future cash flows are equally important
  • Weakness: Timing ignored; averages distort

NPV — Theoretically Superior

Accounts for time value of money; uses all cash flows; gives absolute £ value added. Best for: large strategic investments; comparing projects over different timeframes. Weakness: Requires accurate discount rate and long-term forecasts — both uncertain. Complex for non-financial managers.

Beyond the Numbers

Qualitative Factors in Investment Decisions

A-Level evaluation: A positive NPV is necessary but not sufficient for approval. Qualitative factors — strategic fit, risk, stakeholder concerns — can override strong financial metrics. Real-world investment decisions always combine both.
Risk & Uncertainty

Managing Investment Risk

Practice Question 1

A business invests £80,000. Year 1 inflow: £30,000; Year 2: £30,000; Year 3: £40,000. What is the payback period?

A2 years 3 months
B2 years 6 months
C3 years exactly
D2 years 9 months
B is correct. After Year 1: cumulative = £30,000 (deficit £50,000). After Year 2: cumulative = £60,000 (deficit £20,000). In Year 3, £40,000 arrives — need £20,000 more: 20,000 ÷ 40,000 × 12 = 6 months into Year 3. Total payback = 2 years 6 months.
Practice Question 2

A project costs £250,000 and generates total cash inflows of £400,000 over 4 years. What is the ARR?

A60%
B15%
C37.5%
D40%
B is correct. Total net profit = £400,000 − £250,000 = £150,000. Average annual profit = £150,000 ÷ 4 = £37,500. ARR = (£37,500 ÷ £250,000) × 100 = 15%. A common mistake is dividing total inflows (not profit) by investment, which gives 40% — remember to subtract the initial cost first.
Practice Question 3

A project has a positive payback period but a negative NPV. A manager recommends rejecting it. Which evaluation of this recommendation is most appropriate?

AThe recommendation is wrong — positive payback means the project is profitable
BThe recommendation is likely correct — a negative NPV means the project destroys value in real terms once time value of money is considered
CThe recommendation is wrong — NPV ignores all cash flows after payback
DThe recommendation is correct because payback should always be used ahead of NPV
B is correct. A negative NPV means the discounted present value of cash inflows is less than the initial cost — the project earns less than the required rate of return. The manager's recommendation to reject is sound. A positive payback only means cash is recovered — it does not account for the time value of money or the opportunity cost of capital.
Practice Question 4

A retailer assesses two projects. Project A: NPV = +£150,000, payback = 5 years. Project B: NPV = +£90,000, payback = 2 years. The business has severe short-term cash flow pressure. Which should it choose?

AProject A — higher NPV means it creates more value
BProject B — faster payback is more important when cash flow is under pressure
CProject A — NPV is always the most important criterion
DNeither — both have positive NPVs so neither should be prioritised over the other
B is correct. Despite having a lower NPV, Project B's 2-year payback is critical when the business faces cash flow pressure. A 5-year wait to recover £150,000 may cause insolvency if the business cannot survive that long. Investment appraisal is context-dependent — the "best" method depends on the firm's financial position and risk tolerance.
Summary

Key Takeaways

Use arrow keys or buttons